Loft conversion construction stages:

Week 1

Scaffolding erected. Water tanks moved. Steel beams installed. New floor joists constructed.

Week 2

Velux windows installed. If dormer required, then dormer shell constructed. If gable needed, then gable wall built up as per plans. Flat roof constructed.

Week 3

First installation of electrics, plumbing, and heating.

Week 4

Ceiling taken down above existing stairwell. New stairs fitted. Plasterboard and smooth plaster finish to underside of stairs.

Week 5

Partition walls erected, insulated and plastered. Second installation of electrics, plumbing and heating.

Week 6

The finishing touches. Carpentry work completed including architraves, skirtings and doors. Smoke alarms fitted. Final visit from local authority building control.

Home Conversions

0800 533 5821

Get a FREE quote»

How We Work

We work to a carefully planned schedule for the work we undertake here at NK Conversions, so take the time to peruse our week-by-week plan that culminates in you enjoying your new living space.

Projects can be completed in 5 to 7 weeks - Call us today on 0800 533 5821