Loft conversion construction stages:
Week 1Scaffolding erected. Water tanks moved. Steel beams installed. New floor joists constructed.
Week 2Velux windows installed. If dormer required, then dormer shell constructed. If gable needed, then gable wall built up as per plans. Flat roof constructed.
Week 3First installation of electrics, plumbing, and heating.
Week 4Ceiling taken down above existing stairwell. New stairs fitted. Plasterboard and smooth plaster finish to underside of stairs.
Week 5Partition walls erected, insulated and plastered. Second installation of electrics, plumbing and heating.
Week 6The finishing touches. Carpentry work completed including architraves, skirtings and doors. Smoke alarms fitted. Final visit from local authority building control.